GST On Labour Services Provided for PMAY Housing Project: Ruling
Against M/s Build Layer Constructions
Introduction:
In
a significant ruling impacting subcontractors working on government housing
schemes, the Rajasthan Authority for Advance Ruling (AAR), in its Order No. RAJ/AAR/2025-26/53
dated 23.05.2025, has held that M/s Build Layer Constructions, a
subcontractor engaged in providing labour services for a PMAY-linked project,
is not eligible for GST exemption under Entry 10 of Notification No.
12/2017-Central Tax (Rate) dated 28.06.2017. The authority clarified that
the exemption applies only to pure labour contracts directly related to beneficiary-led
individual housing construction under PMAY.
Applicant
Details
- Name:
M/s Build Layer Constructions
- GSTIN:
08AATFB8617M1Z0
- Ruling Date:
23.05.2025
- Authority:
Rajasthan AAR
Background
M/s Build Layer
Constructions entered into a subcontract with M/s BCM Builders LLP,
which held a main contract with the Rajasthan Government for
construction of 380 flats under the “Affordable Housing Scheme” of the
Pradhan Mantri Awas Yojana (PMAY). The applicant claimed to be supplying pure
labour services for this project.
The applicant approached
the AAR seeking clarity on whether such subcontracted labour supply would be exempt
from GST under Entry 10 of Notification No. 12/2017-Central Tax (Rate).
Questions
Raised
1. Whether
Entry 10 of Notification No. 12/2017-CT(R) dated 28.06.2017 applies to the pure
labour services provided by the applicant?
2. If
not applicable, what would be the HSN classification and applicable GST
rate?
Applicant’s
Submissions
- They are engaged in pure labour
construction services and do not supply materials.
- Their subcontract is with M/s BCM
Builders LLP, the main contractor for the PMAY housing project.
- Entry No. 10 of Notification No.
12/2017 exempts pure labour contracts related to construction under Housing
for All (Urban) Mission / PMAY.
- The exemption is activity-based
and should extend to subcontractors too, since the nature of work
remains unchanged.
Relevant
Legal Provision
Entry No. 10 of
Notification No. 12/2017–Central Tax (Rate):
“Services provided by way
of pure labour contracts of construction, erection, commissioning,
installation, completion, fitting out, repair, maintenance, renovation, or
alteration of a civil structure or any other original works pertaining to the
beneficiary-led individual house construction or enhancement under the Housing
for All (Urban) Mission or Pradhan Mantri Awas Yojana”
→ GST Rate: NIL (exempt)
Observations
by Jurisdictional Officer
- A subcontract does not change the
character of the main contract.
- The benefit of exemption under
the said notification should extend to subcontractors, provided
conditions are met.
- Cited earlier Rajasthan AAR ruling
(RAJ/AAR/2019-20/28) where exemption was granted to a subcontractor
working under PMAY.
AAR’s
Discussion and Findings
Despite favorable
arguments, the AAR made the following key findings against the applicant:
i. Not a Pure Labour
Contract
- The agreement submitted by the
applicant (with BCM Builders LLP) revealed that the applicant is also
responsible for supplying certain machines and materials, not just
labour.
- This violates the “pure labour”
condition under Entry 10 of Notification 12/2017.
ii. Lack of Proof Linking
Main Contract to PMAY
- The applicant was asked to submit documentary
proof that M/s BCM Builders LLP was executing the contract under
PMAY.
- Despite assurance during the hearing,
no proof was submitted within the specified time.
- In absence of evidence, the AAR could
not establish a direct link to PMAY or Housing for All (Urban) scheme.
Final
Ruling
Question
|
Ruling
|
Whether
Entry 10 of Notification No. 12/2017-CT(R) applies?
|
No.
The contract is not pure labour; applicant failed to prove project linkage to
PMAY.
|
What
is the applicable HSN and GST rate?
|
HSN
9954 (Construction Services), specifically under Entry
(xii) of Notification No. 11/2017-CT(R) → 18% GST
|
Conclusion
This ruling serves as a
cautionary precedent for subcontractors in government housing projects:
- Exemption under Entry 10 of
Notification 12/2017 is strictly interpreted.
- To claim the benefit:
- The contract must be exclusively
for labour.
- The end-use must be proven to
be under beneficiary-led PMAY.
- Absence of supporting documentation
or inclusion of material/machinery responsibility disqualifies the
exemption.
Disclaimer: All the Information is based on the notification, circular advisory and order issued by the Govt. authority and judgement delivered by the court or the authority information is strictly for educational purposes and on the basis of our best understanding of laws & not binding on anyone.
Find the Attachment (Press on Click Here )
Click here