GST Vidhi | GST Advance Ruling


M/s HMSU Rollers (India) Pvt. Ltd. Vs. Gujarat Authority for Advance Ruling (GAAR) (AAR Order No.: GUJ/GAAAR/2025/15 / Date of Ruling: 30.04.2025)

ITC On Pre-Engineered Building (PEB) Works and Crane Support Structure: Gujarat AAR Rules Against HMSU Rollers (India) Pvt. Ltd.

Introduction: In a significant ruling, the Gujarat Authority for Advance Ruling (GAAR) denied Input Tax Credit (ITC) on the construction of a Pre-Engineered Building (PEB) and related infrastructure to M/s HMSU Rollers (India) Pvt. Ltd. The AAR held that the supply of materials and services used in constructing a factory building with an overhead crane gantry falls under the blocked credit provisions of Section 17(5) of the CGST Act, 2017.

Case Snapshot

  • Applicant: M/s HMSU Rollers (India) Pvt. Ltd.
  • Application No.: Advance Ruling/SGST & CGST/2024/AAR/06
  • AAR Order No.: GUJ/GAAAR/2025/15
  • Date of Ruling: 30.04.2025

Background of the Case

M/s HMSU Rollers is a manufacturing company undertaking an expansion project that involves the installation of a Pre-Engineered Building (PEB) structure designed to support a 10-ton overhead crane. The PEB includes integrated beams and supports essential for crane operation.

They received a works contract service from M/s Shree Steel Building Technology for installation and erection of the PEB. The company sought clarity on eligibility of ITC on:

  • Steel, cement, and consumables used in the PEB structure.
  • Installation and erection service of the PEB.
  • Other capital goods like crane rails and electrification used to operate the crane.

Questions Before AAR

Whether proportionate ITC is available on:

a) Steel, cement, consumables used in execution of works contract for constructing an integrated factory building (PEB) with gantry beam;

b) Installation and erection services of the PEB used for operating a crane;

c) Capital goods like rails and electrification used for crane operations.

Applicant’s Submissions

  • The PEB is not merely a building but functions as plant and machinery since it directly supports an operational crane.
  • The overhead crane cannot function independently and relies on the load-bearing structure of the PEB.
  • Submitted Chartered Engineer's certificate showing load analysis to demonstrate that the PEB bears the crane’s operational load.
  • Argued that the PEB structure qualifies as “plant and machinery” under the Explanation to Section 17(5) and is therefore eligible for ITC.

Legal Provisions Involved

  • Section 17(5)(c): No ITC for works contract service for immovable property (except for plant and machinery).
  • Section 17(5)(d): No ITC for goods/services for construction of immovable property on own account.
  • Explanation to Section 17: Defines “plant and machinery” as equipment fixed to earth, but excludes civil structures, buildings, land, etc.

Key Findings by the Authority

a) On Steel, Cement, and Consumables (Part a)

  • The PEB structure is classified as an immovable property.
  • It is a civil structure, specifically excluded from “plant and machinery”.
  • ITC is blocked under Section 17(5)(c) and (d).

b) On Erection and Installation of PEB (Part b)

  • Classified as a works contract service under SAC 995441.
  • Since the service is for construction of an immovable structure and not further supplied, ITC is not allowed.

c) On Crane Rails, Electrification, etc. (Part c)

  • If embedded into the civil structure, they become immovable property.
  • Even if they support machinery, once embedded in the PEB, ITC is blocked.

Supreme Court Ruling Relied On

The AAR relied on the landmark judgment in Safari Retreats Pvt. Ltd. (2024 INSC 756), which held:

  • ITC is blocked if used for construction of immovable property.
  • Only exception: if used for “plant and machinery” as per defined scope.
  • Civil structures/buildings are not eligible, even if used in business.

Rebuttal to Tamil Nadu AAAR Decision

The applicant cited a favorable order in Coral Manufacturing Works India Pvt. Ltd. (TN AAAR/04/2023). However, the Gujarat AAR rejected this, stating:

  • That ruling was pre-Supreme Court decision in Safari Retreats.
  • After the apex court’s ruling and Finance Act 2025 amendments, no ITC on civil structure works is permissible.

Final Ruling

The AAR held that no Input Tax Credit is admissible on:

Component

GST Credit Availability

a) Steel, Cement, Consumables used in PEB

Not allowed – Immovable property

b) Erection & Installation of PEB

Not allowed – Works contract for immovable property

c) Crane rails, electrification, etc.

Not allowed – Becomes part of civil structure

 

Conclusion

This ruling reaffirms the strict interpretation of blocked credit provisions under Section 17(5) of the CGST Act. Businesses constructing PEB or similar infrastructure should note:

  • Civil structures, even if used for operating machinery, are excluded from ITC.
  • Works contract services used to build factory buildings are not eligible, unless the asset qualifies as plant and machinery per statutory definition.
  • Proper classification and structure planning are crucial to preserve GST credit eligibility.

Disclaimer: All the Information is based on the notification, circular advisory and order issued by the Govt. authority and judgement delivered by the court or the authority information is strictly for educational purposes and on the basis of our best understanding of laws & not binding on anyone.

Find the Attachment (Press on Click Here )


Click here

Comments


Post your comment here