GST Vidhi | GST Advance Ruling


Shibaura Machine India Private Limited Vs. Authority For Advance Ruling, TAMIL NADU

Eligibility of Input Tax Credit (ITC) on Fire-Fighting System and Public Health Equipment for Factory Expansion

(Advance Ruling No.: 31/ARA/2025 / Date of Ruling: 18 August 2025 / Authority For Advance Ruling, TAMIL NADU / Name of Applicant: M/s. Shibaura Machine India Private Limited)

Summary of the Advance Ruling

The applicant sought a ruling on whether Input Tax Credit (ITC) is admissible on the Fire-Fighting System (FFS) and Public Health Equipment (PHE) installed as part of the factory expansion project for manufacturing activities.
Additionally, the applicant requested clarity on the timeline for availing ITC on invoices related to “advance components” billed by the supplier.

After examining the submissions, contract details, and relevant provisions, the Tamil Nadu Authority for Advance Ruling held that:

  • The installation of the Fire-Fighting System and PHE forms part of immovable property, and
  • The supply constitutes a Works Contract, thus attracting Section 17(5)(c) and (d) of the CGST Act, 2017.

Accordingly, the Authority ruled that ITC is not admissible, and the second question regarding ITC timing was deemed not applicable.

Questions Raised in the Ruling

1.    Whether Input Tax Credit (ITC) is eligible on Fire-Fighting System and Public Health Equipment for expansion of factory for manufacturing activity?

2.    What should be the basis to determine the timeline to avail ITC on the tax invoice raised by the supplier to bill “Advance Component” of the contract?

Relevant Legal Provisions

  • Section 16(1) – Eligibility and conditions for taking ITC
  • Section 17(5)(c) and (d) – Blocked credits for works contracts and immovable property
  • Explanation to Section 17 – Definition of “Plant and Machinery”
  • Section 2(119) – Works Contract definition
  • Section 2(30) – Composite Supply definition
  • Schedule II, Para 6(a) – Works Contract as supply of services

Facts and Submissions by the Applicant

  • The applicant manufactures injection moulding machinery and undertook a project for expanding its manufacturing facility.
  • The total contract value for construction and installation was ₹90.45 crore (exclusive of GST), awarded to M/s. SMCC Construction India Ltd.
  • The contract was divided into four major components:
    • Civil Works – ₹49.30 crore
    • Pre-Engineered Building (PEB) – ₹27.29 crore
    • Fire-Fighting System (FFS) – ₹4.65 crore
    • Public Health Engineering (PHE) – ₹1.74 crore
  • The applicant argued that the FFS and PHE systems consist of apparatus and equipment (hydrant systems, pumps, sprinklers, fire alarms, sewage systems, etc.) which are not embedded in earth, hence movable.
  • They classified these under Plant and Machinery and not as part of the building structure.
  • They relied on:
    • M/s. Nipro India Corporation Pvt. Ltd. (AAR Maharashtra, 2018) – ITC allowed on fire alarm and public address systems.
    • Delhi High Court in CIT v. Hindustan Times Ltd. (2000) – Fire-fighting equipment treated as plant and machinery.
  • The applicant also submitted that Factory Act, 1948 (Sections 38 and 46) mandates fire safety and public health installations, reinforcing that such equipment are essential for factory operations.
  • Regarding advance payment invoices, the applicant contended that ITC can be claimed once the goods/services are received, even if the supply concludes after the due date under Section 16(4).

Discussion and Findings by the Authority

1. Nature of Supply

  • The contract covers Supply, Installation, Testing, and Commissioning of FFS and PHE systems — a composite works contract involving both goods and services.
  • The deliverable is defined as “Permanent Work” in the contract, signifying an immovable nature.

2. Whether Immovable or Movable Property

  • FFS and PHE systems, once installed, are permanently fastened to walls, floors, or ceilings.
  • As per Section 3(26) of the General Clauses Act, 1897, such installations qualify as immovable property.
  • The Authority noted that these systems are integrated into the factory building, losing their independent character after installation.

3. Applicability of Section 17(5)

  • Both Section 17(5)(c) and (d) block ITC for works contracts and for goods/services used in the construction of immovable property.
  • The Authority concluded that the fire-fighting and sanitary systems form part of immovable property and are thus ineligible for ITC.

4. Whether Equipment Qualifies as “Plant and Machinery”

  • The term “plant and machinery” applies only to equipment used directly for making outward supply of goods or services.
  • The FFS and PHE systems support factory operations (safety, sanitation) but do not directly participate in the manufacturing process.
  • Hence, they do not qualify as plant and machinery under the statutory definition.

5. Case Law References

  • The Authority found that earlier rulings such as Nipro India Pvt. Ltd. (allowing ITC) were distinguishable.
  • It relied instead on:
    • Embassy Industrial Parks Pvt. Ltd. (KAR AAR 109/2019) – Fixtures like fire systems form part of building infrastructure and are immovable.
    • Varachha Co-operative Bank Ltd. (Gujarat AAAR, 2023) – Fire extinguishers permanently fixed to a building are immovable; ITC blocked.

6. Second Question – Timeline for ITC

  • Since ITC on the main contract is not admissible, the question on timing of ITC availment on advance invoices was declared infructuous.

Ruling / Decision

1.    Eligibility of ITC: Input Tax Credit on Fire-Fighting System and Public Health Equipment installed for factory expansion is not admissible, being blocked under Sections 17(5)(c) and (d) of the CGST/TNGST Acts, 2017.

2.    Timeline for Availing ITC: Since ITC itself is ineligible, the timeline question does not arise.

 

Conclusion

The Authority for Advance Ruling, Tamil Nadu, concluded that:

  • Fire-fighting and public health installations constitute immovable property, and
  • The related works qualify as “Works Contract Services”, which are ineligible for ITC under Section 17(5).
    The AAR reaffirmed that only machinery or equipment directly involved in the manufacturing or outward supply process qualifies as “plant and machinery” eligible for ITC.

Accordingly, M/s. Shibaura Machine India Pvt. Ltd. was denied ITC on these installations, and its query on ITC timing was rendered redundant.

 Disclaimer: All the Information is based on the notification, circular advisory and order issued by the Govt. authority and judgement delivered by the court or the authority information is strictly for educational purposes and on the basis of our best understanding of laws & not binding on anyone.

Press On Click Here To Download Order File


Click here

Comments


Post your comment here